Orange Barrel Alert – Creekside Drive Reconstruction

Creekside Drive Reconstruction

Creekside Drive Reconstruction

Beginning the week of March 30, 2015. Southlake Public Works will begin the  reconstruction of Creekside Drive from the 1600 block, north to the Cul de Sac.

Crews will:

  • Remove the current asphalt drive surface
  • pulverize and stabilize of the existing sub grade
  • resurface the street with 4″ asphalt drive surface

Creekside Drive will remain open to its residents during the construction but some brief delays should be anticipated during the hours of 7:00 a.m.- 5:00 p.m. Monday- Friday. Emergency services, postal services, trash collection, deliveries, and Carroll Independent School District  busing will have access at all times during construction hours.

The project is anticipated to be completed by May 1, 2015 (weather permitting).

For any questions, please contact Southlake Public Works Operations at (817) 748-8082.