Champions Club Construction Continues Toward Late 2018 Completion

The Marq Southlake continues to see ongoing construction of Champions Club, the second and final phase of development for the multi-faceted community center. Now at approximately 58 percent complete, Champions Club is on schedule for a late 2018 grand opening.

The premier activity hub will offer 82,000 square feet of state-of-the-art amenities and fitness equipment, including a fitness center, a gymnasium with two full courts, an indoor pool with sauna and spa, and much more.

“Concrete, masonry, windows, skylights, metal framing, painting, plumbing, electrical, air conditioning and pool specialty trades continue to work to meet scheduled milestones. Initial finish work for ceilings above the cabanas has started while the installation of the exterior brick veneer is almost complete,” stated Rob Cohen, the Director of Public Works for the City of Southlake.

Electrical power is expected to be connected to Champions Club in early July. Air conditioning and other mechanical systems are scheduled to be operational later in the month. Be sure to check out the building progress in real-time with the construction camera.

An image of a family bowling and dining

Photo of a solar eclipse