N. White Chapel Widening Project On Schedule and Making Major Headway

The end of the school year is right around the corner and while that means summer break for many, it’s rock and roll time for the N. White Chapel widening project. N. White Chapel from Highland to SH 114 will have a totally new look by the time school is back in session.

Despite some intervention from Mother Nature with some heavy rain falls, the project is pretty much on schedule. Most recently in mid-April, crews closed a section of east Highland to begin construction of the east side of the dual-lane roundabout.

If you’ve driven through the N. White Chapel and Highland intersection, you can see the roundabout starting to take shape. The old pavement has been removed and crews are working on leveling the surface in preparation to pave. Work on this side of the roundabout is expected to be completed by early June so work on the other side of the roundabout can begin.

New pavement is in on the southbound lanes and is closer to joining with the existing pavement close to the intersection of N. White Chapel and SH 114. Meanwhile what’s left to pave on the northbound traffic side is formed up to be ready to pave. Weather permitting the contractor hopes to have paving of the new traffic lanes completed in a few weeks.

“It’s great to be able to actually see the roundabout taking shape,” notes City Engineer and Deputy Director of Public Works Kyle Hogue. “So far 70 percent of the work has been completed. Up next is the completion of the roundabout, installation of public art in the roundabout, landscaping and new sidewalks.”

As with any construction project, drivers are encouraged to be extra aware of their surroundings and if possible avoid the area.

In the meantime, if you haven’t already, follow Southlake Mobility on Facebook for all the up-to-date mobility news in Southlake. You can also visit the website at www.ConnectSouthlake.com.