N. White Chapel Project November 2020 Update

There has been a lot of roadwork happening on W. Chapel Downs lately. The construction on this road is a major component of the N. White Chapel Widening Project because it intersects with N. White Chapel and is adjacent to other roads that lead to the major intersection.

Over the last few weeks, contractors have worked to complete paving on W. Chapel Downs and storm drain installation on E. Chapel Downs.

E. Chapel Downs has been closed from N. White Chapel Boulevard to Saratoga Drive and traffic has been shifted to the east of W. Chapel Downs to allow drainage installation.

The drainage installation on Chapel Downs is expected to be completed within six to eight months, weather permitting.

Contractors have completed the excavation of excess dirt on N. White Chapel to grade the road and asphalting of the temporary road has started. Striping is estimated to start next week.

The entire project is estimated to be completed by Spring 2022, weather permitting.

The total N. White Chapel Widening Project is estimated to cost around $17 million.

For more N. White Chapel construction updates, follow the Southlake Mobility Facebook page or sign up for the Mobility e-newsletter.