June 3, 2021

2021 Mid-Year Mobility Progress Report

June marks the mid-year point for 2021 mobility projects, and we have made major progress. Here’s where we are: Road reconstruction projects Earlier this year, the Southlake Mobility Team rolled out the 2021 road reconstruction projects. These projects included repaving, repairing potholes and full road reconstruction for Brookwood Lane, Hillcastle Street and Roadtree Drive, Briar […]

June marks the mid-year point for 2021 mobility projects, and we have made major progress.

Here’s where we are:

Road reconstruction projects

Earlier this year, the Southlake Mobility Team rolled out the 2021 road reconstruction projects. These projects included repaving, repairing potholes and full road reconstruction for Brookwood Lane, Hillcastle Street and Roadtree Drive, Briar Lane, Hilltop Drive, Hillside Court and Simmons Court.

All construction on these roads was completed in May.

White Chapel

Drainage installation on the west side of the road is now complete. Subgrade stabilization will take place within the next couple of weeks.

The N. White Chapel Widening Project is scheduled to be completed by spring 2022, weather permitting.

Carroll Avenue Paving Project

The Carroll Avenue Paving Project commenced last week. Contractors have been on site all week repaving Burney Lane to the Dove Road roundabout.

This portion of the project is expected to be completed by Tuesday, June 18, weather permitting.

The entire project is expected to be completed by August 2021, weather permitting.

For more updates on road construction projects, please follow the Southlake Mobility Facebook page or visit www.ConnectSouthlake.com.

 

 

 

 

 

 

 

 

 

Image shows Santa and Mrs. Claus along with two people dressed up as nutcrackers
linkedin facebook pinterest youtube rss twitter instagram facebook-blank rss-blank linkedin-blank pinterest youtube twitter instagram