Orange Barrel Alerts Starting on May 31, 2023

Here’s a look at what’s going on with Connect Southlake projects and how these may affect you and your travels.

May 31 – June 7

Water Improvements Along S. Pearson Lane and Union Church Road

Contractors are set to perform vacuum excavation services to locate subsurface utilities along S. Pearson Lane and Union Church Road, from FM 1709 to FM 1938, and E. Dove Road from Estes Park Drive to west of North Carroll Avenue starting Wednesday, May 31, 2023 through Wednesday, June 7, 2023, from 7 a.m. – 5 p.m., weather permitting. Shoulder work will take place during this time and should not disrupt traffic. This work is being done in anticipation of the upcoming Capital Improvement Project for waterline improvements along S. Pearson Lane and Union Church Road, E. Dove Road, and Oak Bend Court.

OBA S Pearson Ln- Water Improvements

 

June 1 – 9

Storm Drain Work on Lonesome Dove Road

Water Utilities will conduct lane closures along Lonesome Dove Road to construct a storm drain pipe. The lane closures will occur from June 1, 2023, through June 9, 2023, weather and material delivery permitting.

Map of Lonesome Dove Road

 

June 5

Water Improvements Along East Dove Road and Oak Bend Court

Contractors are set to begin work on the Water Distribution System Improvements at S. Pearson Lane & Union Church Road, E. Dove Road, and Oak Bend Court on Monday, June 5, 2023. During this time, it will be necessary to temporarily disrupt traffic along S. Pearson Lane & Union Church Road, from FM 1709 to FM 1938, and E. Dove Road from Estes Park Dr. to the west of North Carroll Avenue. This work is expected to last through the Winter of 2024, weather permitting.

OBA-Dove-Rd-Oak-Bend-Ct-Water-Improvements

 

June 5 – 16

Road Rehab Project on Jellico Circle

Public Works and Tarrant County will begin road rehab work on Jellico Circle starting June 5, 2023. The project should continue until June 16, 2023, weather permitting. Daily hours of operation will be from 7 a.m. to 4 p.m. Jellico Circle will remain open to through traffic throughout the project with traffic control.

OBA FY23' ILA Jellico Cir - Road Rehab

 