October 19, 2021

Progress Report: Fall 2021 Mobility

It is officially fall! The seasons may change but improving our roads, pathways and sidewalks never stops. Here is where we are on mobility projects: E. Bob Jones Road: Completed Paving on E. Bob Jones Road was completed in September 2021. Big Bear Creek Bridge: Completed After several months of construction, the Big Bear Creek […]

It is officially fall!

The seasons may change but improving our roads, pathways and sidewalks never stops.

Here is where we are on mobility projects:

E. Bob Jones Road: Completed

Paving on E. Bob Jones Road was completed in September 2021.

Big Bear Creek Bridge: Completed
After several months of construction, the Big Bear Creek Bridge Project is now completed. The bridge is located at the Colleyville and the Southlake border where White Chapel Boulevard turns into Pleasant Run Road. Work on the bridge was determined by an assessment to replace the bridge. This effort was in partnership with the City of Southlake, City of Colleyville and Texas Department of Transportation. The project was completed in September 2021.

White Chapel Boulevard Project: In-Progress
Work on N. White Chapel Boulevard is moving forward. Contractors recently repaired the subgrade and are currently filling the inlet boxes.

Masons are finishing up the back side of the screening wall and irrigation crews have been adjusting residents’ irrigation.

Cement stabilization is set to take place the week of October 18, weather permitting.

The full project is expected to be completed by spring 2022, weather permitting.

For more information, including updates on construction projects, follow the Southlake Mobility Facebook page or visit www.ConnectSouthlake.com.