Construction Brief – S. Carroll Avenue Widening Project Begins

City of Southlake road crews began placing  signs and barricades in preparation of construction of a new third lane on South  Carroll Avenue between Southlake Blvd and Lakes of La Paloma Court.

The third lane will improve the level of service traffic conditions by creating a two way center left turn lane along this section of S. Carroll Avenue.  Upon completion of the new third lane, northbound traffic entering (turning westbound) into the new Winding Creek Addition will not impede the northbound traffic on S. Carroll Ave.

Drivers who use these streets are requested to use extra caution as trucks and equipment will be entering and exiting the project area.  Flaggers will be present during work hours and delays can be expected during the hours of construction – 8:00 a.m. to 4:00 p.m.).

Two lanes of traffic on S. Carroll Avenue will be provided with the exception of minor delays.  Motorists who are able to use alternative routes are recommended to do so.

The project is funded through Roadway Impact Fees paid to the city by the developer of the Winding Creek Development.  The project is expected to be completed by the end of November.

Construction Brief for DPS North Facility Project

The DPS North project site is located at the northeast corner of E. Dove Rd. and N. White Chapel Blvd. The proposed facility will support Fire and EMS operations in the north side of the City and double as a training facility for both police and fire personnel. It will include a one story building to house training classrooms and a fire station, an indoor firing range and the potential for a four story training tower.

Here is a brief update on the project:

  • The parking lot is 85% complete with landscaping and irrigation installation in progress. Light poles will be installed next month.
  • Foundation piers for the firing range are 95% complete. The piers for the Fire Station foundation have been installed and foundation grade beams for the fire station are being formed currently.
  • Storm sewer utilities are 50% complete and underground electrical conduits are currently being installed.
For more information, click here.