Earlier this week, Public Works Streets and Drainage crews dug test pits to prepare for construction at the intersection of the southbound lanes at Zena Rucker Road and S. Carroll Avenue.
With the extension of Zena Rucker Road approaching completion, traffic is expected to increase in the area as shoppers and pedestrians travel to the Shops of Southlake. The S. Carroll Avenue CIP project will turn the asphalt lane into a concrete lane so the entire roadway will be comprised of the same material for a more long-term use and future expansion.
The project is estimated to start within two weeks and completed in six weeks, weather permitting.
The improvements are a part of the 2030 Master Mobility Plan.
For more information about mobility projects in Southlake and updates on mobility news, follow our Southlake Mobility Facebook page.