Wednesday, June 29, 2022

Landscaping is in on FM 1938

The median landscaping on FM 1938 is starting to come together as the City’s contractor wraps up its work.

Meanwhile, the contractor continues to prepare for the construction of the Myers Meadow screening wall. Once construction of the screening wall begins, lane closures will be in place for the duration of the project.

The lane re-configuration at the north end of FM 1938, north of Beam Drive, is still in place as the drainage improvements are ongoing. Drivers can expect the lane switch to remain in place until further notice.

As a reminder, while construction work is being completed, the entire FM 1938 corridor is considered a construction zone and the current speed limit of 30 mph will remain in place until the project is complete.

Stay up-to-date with construction updates by following the Southlake Mobility page on Facebook.

FM 1938 Landscape Median

New landscaping in on FM 1938

FM 1938 Landscape Trees

New trees in on FM 1938

Progress continues on FM 1938

Construction work along FM 1938 continued to make progress in the month of April.

Utility relocation along the Myer’s Meadow subdivision is underway. Tri-County Electric has completed their relocates while the other utility relocations are underway. Once utility work is complete construction of the screening wall will begin. Lane closures are expected for the duration of the screening wall construction.

TxDOT’s contractor continues to make headway on the underground drainage structure north of Beam Drive. The structure is being constructed to provide flood protection for the properties downstream of FM 1938.

This northern portion of the project is expected to be complete by next winter.

As a reminder, while this construction work is being completed, the entire corridor is considered a construction zone and the construction speed limit of 30 mph will remain in place until the project is complete.