South White Chapel Boulevard Reconstruction Complete

Reconstruction of S. White Chapel by Public Works Street crews

Reconstruction of S. White Chapel by Public Works Street crews

The South White Chapel Boulevard joint reconstruction project with Tarrant County Precinct 3 is complete.

The project, which began in June, was a joint project in partnership with Tarrant County to reconstruct/rehabilitate South White Chapel Boulevard from the Continental roundabout south to the Colleyville city limit line.

The scope of the project included:

  • Re-constructing the sub-grade and installing ribbon curb for pavement confinement and structural integrity.
  • Foundation work that consisted of installing 8-inches of sub-grade and 6-inches of pavement surface for a total 14-inch depth.
  • The bridge at the southern portion of the roadway was also milled and overlayed with new asphalt following the structural improvements that were made to that bridge earlier in the year.

Partnering with Tarrant County is an annual effort to reconstruct/rehabilitate roads within the City limits. Not only does this partnership provide cost-savings to the City, it also supplements one of the Public Works Department’s goals to develop, build and maintain a high quality transportation infrastructure. In the end, maintaining City streets is critical to improving mobility and ensuring the safety and security of motorists traveling on Southlake’s roads.

For more information about the Street Rehabilitation Participation Program, click here. For questions, please contact the Public Works Department at 817-748-8079.

Orange Barrel Alert – Creekside Drive Reconstruction

Creekside Drive Reconstruction

Creekside Drive Reconstruction

Beginning the week of March 30, 2015. Southlake Public Works will begin the  reconstruction of Creekside Drive from the 1600 block, north to the Cul de Sac.

Crews will:

  • Remove the current asphalt drive surface
  • pulverize and stabilize of the existing sub grade
  • resurface the street with 4″ asphalt drive surface

Creekside Drive will remain open to its residents during the construction but some brief delays should be anticipated during the hours of 7:00 a.m.- 5:00 p.m. Monday- Friday. Emergency services, postal services, trash collection, deliveries, and Carroll Independent School District  busing will have access at all times during construction hours.

The project is anticipated to be completed by May 1, 2015 (weather permitting).

For any questions, please contact Southlake Public Works Operations at (817) 748-8082.