The Shady Oaks Drive street rehabilitation project enters the home stretch and is on track to meet its mid- August completion date.
Public Works Streets crews have been working hard to finish the street rehabilitation along Shady Oaks Drive. The project, which began June 16, 2016 and is this year’s street rehabilitation collaboration with Tarrant County Precinct 3, has made significant repairs and corrections to the segment of Shady Oaks from the north property line of Bicentennial Park to West Highland Street. To date, crews have paved and added new layers of asphalt to the road (see photo).
Although the work may look complete, there are some items that remain. This week, you’ll see crews back-fill and complete sod work. In addition, crews will:
The Shady Oaks street rehabilitation project is expected to be complete before school starts on Monday, August 22, 2016.
For questions, please contact Public Works Operations at 817-748-8079.
Beginning the week of March 30, 2015. Southlake Public Works will begin the reconstruction of Creekside Drive from the 1600 block, north to the Cul de Sac.
Crews will:
Creekside Drive will remain open to its residents during the construction but some brief delays should be anticipated during the hours of 7:00 a.m.- 5:00 p.m. Monday- Friday. Emergency services, postal services, trash collection, deliveries, and Carroll Independent School District busing will have access at all times during construction hours.
The project is anticipated to be completed by May 1, 2015 (weather permitting).
For any questions, please contact Southlake Public Works Operations at (817) 748-8082.