N. White Chapel Project December 2020 Update

Construction on N. White Chapel Boulevard is forging ahead. The asphalting and striping of the temporary road is complete from Mission Drive to Emerald Drive. Crews are working to install drainage boxes at S. School Drive and Dragon Drive, and the excavation process for the new road from Chapel Downs to Unity Way has started.…

Construction on N. White Chapel Boulevard is forging ahead.

The asphalting and striping of the temporary road is complete from Mission Drive to Emerald Drive.

Crews are working to install drainage boxes at S. School Drive and Dragon Drive, and the excavation process for the new road from Chapel Downs to Unity Way has started.

Drainage installation is also taking place from Chapel Downs to 1020 N. White Chapel Blvd. As soon as this section is completed, drainage installation from Chapel Downs to the water tower located at the 400 block of N. White Chapel Blvd. will commence.

Chapel Downs has been closed at N. White Chapel Boulevard and traffic has been detoured to Ascot Drive.

This portion of the project is estimated to last between six and seven months.

The N. White Chapel Widening Project is estimated to cost $17 million and is scheduled to be completed by spring 2022, weather permitting.

For more N. White Chapel construction updates, follow the Southlake Mobility Facebook page or sign up for the Mobility e-newsletter.