N. White Chapel Project Update October 2021

The paving portion of the N. White Chapel Boulevard Widening Project is 65% complete. All work for underground utilities and drainage, including the inlet boxes, is also complete. Currently, masons are finishing up the back side of the screening wall along the east side of N. White Chapel Boulevard. Last week, irrigation adjustments were made […]

The paving portion of the N. White Chapel Boulevard Widening Project is 65% complete.

All work for underground utilities and drainage, including the inlet boxes, is also complete.

Currently, masons are finishing up the back side of the screening wall along the east side of N. White Chapel Boulevard.

Last week, irrigation adjustments were made to residents’ back yards and topsoil was delivered to the site for landscaping.

Cement stabilization is set to take place over the next few weeks, weather permitting.

The N. White Chapel Widening Project is scheduled to be completed by spring 2022, weather permitting.

For more N. White Chapel Boulevard construction updates, follow the Southlake Mobility Facebook page or sign up for the Mobility e-newsletter.