Work on N. White Chapel Boulevard is on the move. Contractors have finished the excavation process for the northbound lanes and utility crews are finishing up installing the remaining storm lines and water connections. Plans to install curb inlet boxes on the east side of the road are in the works. Final adjustments will be…

Work on N. White Chapel Boulevard is on the move.

Contractors have finished the excavation process for the northbound lanes and utility crews are finishing up installing the remaining storm lines and water connections.

Plans to install curb inlet boxes on the east side of the road are in the works.

Final adjustments will be made to the elevation within the next two weeks.

Paving of the northbound travel lanes is expected to be completed within the next three months, weather permitting.

The N. White Chapel Widening Project is scheduled to be completed by spring 2022, weather permitting.