Although this Texas weather has a mind of its own and can have adverse effects on projects, work on N. White Chapel is on schedule.

Waterline work is ongoing at each of the N. White Chapel intersections from Emerald to Ascot. The anticipated completion date for this work will be February 14.

Street light installation is in the works along Highland to SH 114, weather permitting and will soon be followed by, median landscaping, the replacement screening wall on the East Side of N. White Chapel, along with sidewalks and a traffic signal at Ascot Drive.

This project is expected to be completed by spring 2022 with total estimated cost of $17 million for both projects.

For more updates on Mobility projects, follow the Southlake Mobility Facebook page or visit www.ConnectSouthlake.com.