Roundabout at N. White Chapel and Highland on Track to Open Before School Starts

The end of summer is upon us and that means back to the school year routine. It also means the morning commute is about to pick up again. For many that commute will remain unchanged, however, N. White Chapel drivers will have a new addition to their route. Despite a heavy rainy season, construction crews are still on track to open the new roundabout at N. White Chapel and Highland before the start of school. While the ultimate configuration will be dual lane, it will temporarily function as a single lane while the median work is completed.

The roundabout is just one part of the two phase N. White Chapel widening project. In the past weeks, crews have been working on the west leg of the roundabout. About half of the concrete work has been completed in anticipation for the asphalt work that is expected to start next week, weather permitting.

“The spring rain did unfortunately cause us to have to rearrange our schedule a bit, but our contractor was able to work around it to keep the project moving forward,” noted City Engineer and Deputy Director of Public Works Kyle Hogue. “We’re looking forward to having the roundabout open and traffic flowing on east and west Highland again.”

While the roundabout is a major component of the first phase of the widening project, crews have also been working on widening N. White Chapel between Highland and SH 114. In the last week, work has been started on the new median near the SH 114 intersection.

Once completed, the final stages of the project will include striping of the new traffic lanes, new sidewalks, landscaping and the installation of public art in the roundabout. Construction on this phase of the project is expected to finish up this fall with utility work on the second phase of project starting as well. Phase 2 is the widening of N. White Chapel from Emerald to Highland.

New lane configuration is on the horizon for the intersection of N. White Chapel and SH 114. Crews also plan to have one lane northbound and one lane southbound open for the intersection prior to school starting as well. Again the interior lanes will remain closed until all median work is complete. As always, drivers are reminded to use extra caution when driving through the construction zone, travel at or below the posted speed limit and keep an eye out for construction workers in the area.

In the meantime, if you haven’t already, follow Southlake Mobility on Facebook for all the up-to-date mobility news in Southlake. You can also visit the website at www.ConnectSouthlake.com and sign up for the Mobility Newsletter.

2019 Brings More Progress on N. White Chapel Widening Project

With the New Year comes the excitement for new things to come. In Southlake, 2019 will bring a new and improved N. White Chapel Boulevard.

Crews have been steadily making progress on the widening of N. White Chapel between Highland Street and SH 114. Part of a larger N. White Chapel improvement project, when completed there will be a new dual-lane roundabout at Highland and N. White Chapel. Gone will be the two-lane road motorists are used to, and in its place will be landscaped divided four-lane road.

 

 

 

 

 

 

 

 

 

 

The second part of this Capital Improvement Project will be the widening of N. White Chapel from Emerald Boulevard to Highland. When completed, N. White Chapel will be a four-lane road from FM 1709 to SH 114.

Since spring 2018 crews have:

  • Installed a new 12-inch water line
  • Installed new sanitary sewer lines
  • Installed new storm drains
  • Paved portions of the roundabout, and
  • Paved portions of north and southbound lanes

“We are pleased with the progress of this project. It will be a much-needed improvement,” noted Public Works Director Rob Cohen. “It was a wet fall, but despite the rain, we still made significant progress and are still on track for a fall 2019 completion of this phase of the overall improvement. The additional lanes and new roundabout will make a positive difference for motorists on this section of N. White Chapel.”

As the project continues to move forward, motorists can expect lane switches and lane closures, however, two-way traffic will be maintained throughout the project. As always, motorists are reminded to use caution and be aware of their surroundings as they drive through the construction zone.

For updates follow Southlake Mobility on Facebook and visit www.ConnectSouthlake.com.

NWC No border utilities

Orange Barrel Alert: North Peytonville Ave Reconstruction

On Thursday, June 1st, crews will begin road reconstruction and curb installation in the N. Peytonville Ave. area. The project starts at the N. Peytonville Ave. intersection with Corporate Circle and runs north to Ten Bar Trail.

Expect traffic delays and possible lane closures between 8:00 AM – 3:00 PM on weekdays. Please seek alternate routes if possible. Weather permitting, the project expected completion date is Saturday, August 5th.

This roadway project is part of the City of Southlake’s inter-local partnership with the Tarrant County Precinct 3 Roadway Maintenance Division. The purpose of this inter-local agreement is to reduce taxpayer costs for roadway maintenance through combining City and County resources to quickly and efficiently complete construction. Director of Public Works Robert Cohen stated, “Roadway reconstruction projects such as this are vital to the continued reliability and safety of our City’s pathways. We are very thankful for our partnership with Tarrant County as we collectively work to improve mobility in Southlake.”

If you have any questions or concerns, please contact Southlake Public Works Operations at 817-7489-8082.