Due to a shortage of one of the main ingredients in concrete in the D/FW metroplex, the Southlake Public Works Department made the decision to create a temporary batch plant to complete the N. White Chapel Project on schedule.

A temporary batch plant, or concrete mixing plant, will be brought on the east side of N. White Chapel Boulevard between E. Highland Street and Ascot Drive so that necessary materials are available to complete the project in a timely manner. Without the temporary batch plant, the project will be delayed, possibly as long as six months.

The location was chosen because it met Texas Commission on Environmental Quality (TCEQ) requirements and was near the construction site. Other reviewed sites could have taken 4-6 months to be approved.

The temporary batch plant will operate in two phases. The first phase will require the plant to be open for four weeks. Approximately 6-8 weeks later, the plant will operate for another four weeks. The plant will then be removed.

The plant will operate during normal project work hours, from 7 a.m. - 7 p.m., Monday – Friday. On occasion, the plant may be open on Saturday. Deliveries to the plant will be made outside of traffic rush hours.

Residents can expect muffled generator or vehicle noises. A water truck and sweeper will be onsite to minimize windblown dust and keep the area clear of material.

More information about the temporary batch plant can be found at: www.CityofSouthlake.com/NorthWhiteChapel. For questions or concerns, please contact the Public Works Department at 817-748-8098.

There are many ongoing construction projects throughout the City of Southlake. Each project seems to march to a specific rhythm that translates to physical progress. This progress can be seen when you look at a project every few days.

Some projects seem to lag or even take a step or two backward. There are good reasons for many of the occurrences that you may see out in the field. These reasons are as numerous as the different project types.

Let's narrow this discussion to the North White Chapel roadway widening project. Specifically, let's look at the work taking place at the intersection of North White Chapel and Chapel Downs.

The contractor is working to install a new drainage system that will be placed under the roadway when all of the work has been completed. The contractor is slowly working along West Chapel Downs. The contractor digs. New drainage pieces are installed. The contractor closes up the hole and starts the process all over again.

The contractor works this way because the City directed the contractor to keep the existing drainage system operational while the new system is constructed. There will be a point in the project when the old and new systems will come together. The work on West Chapel Downs is expected to be completed in the coming weeks.

The contractor will then move to start work on East Chapel Downs. The area is different and the requirements are different. The contractor will use a different method and technique for this portion of the work. The entrance at North White Chapel and East Chapel Downs will also be closed for several weeks to complete this part of the project.

Want to keep up with all of our mobility construction updates? Follow us on our Southlake Mobility Facebook page or sign up for the bi-weekly Mobility e-newsletter!

linkedin facebook pinterest youtube rss twitter instagram facebook-blank rss-blank linkedin-blank pinterest youtube twitter instagram